NB! For each new outcome of a risk, a NEW evaluation must therefore be made. The outcome is tagged during evaluation under the heading "Connection". The outcome must then be unique compared to other outcomes. For each outcome, only RE evaluation shall be carried out later without making any changes to the Connection fields. So - if you are to make an evaluation of an outcome that has already been evaluated, you must RE evaluate this risk (not a NEW evaluation) as this picture illustrates:
...
A NEW evaluation uses the plus icon and RE evaluation uses the "repeat" icon. When doing RE evaluations, you will build up a history of this outcome for probability and consequence and be able to see graphs of the development of the risk outcome. In addition, you will be able to see all measures that have been implemented over time and what effect these have had.
...